Standard Practice for Sampling Aggregates
Automaticky preložený názov:
Štandardná prax pre odber vzoriek Agregáty
NORMA vydaná dňa 10.7.2003
Označenie normy: ASTM D75-03
Poznámka: NEPLATNÁ
Dátum vydania normy: 10.7.2003
Kód tovaru: NS-38608
Počet strán: 5
Približná hmotnosť: 15 g (0.03 libier)
Krajina: Americká technická norma
Kategória: Technické normy ASTM
Keywords:
aggregates, exploration of potential sources, aggregates, number of sizes needed to estimate character, aggregates, sampling, ICS Number Code 91.100.30 (Concrete and concrete products)
Significance and Use | ||||||||||||||||
Sampling is equally as important as the testing, and the sampler shall use every precaution to obtain samples that will show the nature and condition of the materials which they represent. Samples for preliminary investigation tests are obtained by the party responsible for development of the potential source (Note 2). Samples of materials for control of the production at the source or control of the work at the site of use are obtained by the manufacturer, contractor, or other parties responsible for accomplishing the work. Samples for tests to be used in acceptance or rejection decisions by the purchaser are obtained by the purchaser or his authorized representative. Note 2—The preliminary investigation and sampling of potential aggregate sources and types occupies a very important place in determining the availability and suitability of the largest single constituent entering into the construction. It influences the type of construction from the standpoint of economics and governs the necessary material control to ensure durability of the resulting structure, from the aggregate standpoint. This investigation should be done only by a responsible trained and experienced person. For more comprehensive guidance, see the Appendix. |
||||||||||||||||
1. Scope | ||||||||||||||||
1.1 This practice covers sampling of coarse and fine aggregates for the following purposes: 1.1.1 Preliminary investigation of the potential source of supply, 1.1.2 Control of the product at the source of supply, 1.1.3 Control of the operations at the site of use, and 1.1.4 Acceptance or rejection of the materials. Note 1— Sampling plans and acceptance and control tests vary with the type of construction in which the material is used. Attention is directed to Practices E 105 and D 3665. 1.2 This standard does not purport to address all of the safety concerns, if any, associated with its use. It is the responsibility of the user of this standard to establish appropriate safety and health practices and determine the applicability of regulatory limitations prior to use. |
||||||||||||||||
2. Referenced Documents | ||||||||||||||||
|
Poskytovanie aktuálnych informácií o legislatívnych predpisoch vyhlásených v Zbierke zákonov od roku 1945.
Aktualizácia 2x v mesiaci !
Chcete vedieť viac informácii ? Pozrite sa na túto stránku.
Posledná aktualizácia: 2024-12-22 (Počet položiek: 2 217 000)
© Copyright 2024 NORMSERVIS s.r.o.