Well Construction Interface Document Guidelines
NORMA vydaná dňa 1.12.2013
    
        Označenie normy: API BULL 97-ed.1
                
                
                
               
                Dátum vydania normy:  1.12.2013
        Počet strán: 28
Približná hmotnosť: 84 g (0.19 libier)
        Krajina:          Americká technická norma
        Kategória: Technické normy API
        
                
              
API BULL 97, 1st Edition, November     2013 - Well Construction Interface Document Guidelines
 This     bulletin provides guidance on information that is to be shared regarding     well construction and rigspecific operating guidelines. It is intended to     align the lease operators safety and environmental management system     (SEMS) with drilling contractors safe work practices (CSWP). 
The     well construction interface document (WCID) is used to formalize the     exchange of information as shown in Figure 1. 
NOTE The WCID is not     intended to duplicate the health, safety, and environment (HSE)     information addressed by the lease operators HSE bridging document with     the drilling contractor. 
The WCID-SEMS is a bridging document that     includes the elements identified in API 75 within the context of well     construction activities. It is understood that work processes vary between     operators and contractors, which should be honored in the development of     the WCID document. 
The intent of the bridging document between the     lease operators SEMS and the CSWP is to provide: 
a) an outline of     responsibilities for the lease operators and drilling contractors     personnel; 
b) acknowledgement that management of change (MOC) and     risk assessment processes should be used: 
- during well     construction activities, 
- to address personnel or organizational     changes to ensure personnel skill level is sufficient for the applicable     position; 
c) a vehicle for the drilling contractor to be involved     when operational changes and/or conditions are identified that could     require a well activity risk assessment; 
d) a method to align all     parties with regard to drilling HSE standards and applicable regulatory     requirements; e) a method of communicating stop work authority.     
The WCID-well plan contains the following elements (shown in     Figure 1): 
a) well design: 
- location and environment,     
- geological and geophysical; 
b) well barrier plan risk     identification; 
c) well execution plan. 
To enhance safe     operations, the well plan provides a basis for discussion of well     construction equipment, barriers, risks, and the mitigations for those     risks. 
EXAMPLE Drilling contractor rig-specific operating     guideline examples: 
a) well control practices: 
- shut-in     procedures, 
- blowout preventer (BOP) configuration; 
b)     equipment constraints: 
- rig capacity; 
c) well-specific     operating guidelines: 
- watch circle.